As per the memorandum No.
2020/5 (“Memorandum”) issued by the Presidency of Turkey published in the Official Gazette dated April 2,2020 No. 31087; government contractors which
contend their contracts has been temporarily
or permanently, partially or absolutely became impossible to perform due to
Covid-19 shall apply to the relevant authority with documents evidencing the
government contractor’s claim.
Memorandum applies to
government contract executed as per Public Procurement Law No. 4734 (including procurements
excepted) and procurements exempted from this law which also covers defense and offset contracts.
Memorandum states that government
contractor’s applications will be examined by the relevant authority within the
framework of article 10 of the Public Procurement Contracts Law No. 4735.
Additionally, the authority will make its determination in consultation with
the Ministry of Treasury and Finance’s.
Article 10 of Law No 4735
recognizes the following events as force majeure; natural disasters, legal
strikes, epidemic cases, announcement of partial or general mobilization.
Article 10 states that the authority which is party to the government contract may
recognize similar circumstances in case such circumstances have the following
aspects; a) The incident did not arise out of contracting parties’ commitment
or omission, ; b) The incident
constitutes an obstacle in fulfilling the contractual obligations; c) The
contractor could not afford to remove such obstacle ; d) The contractor has notified the
contracting entity in writing within twenty days as of the date which the force
majeure has occurred; e) The incident has been documented / certified by competent
authorities.
As per relevant precedents,
for an incident to be considered as a force majeure under the Article 10 of Law
No 4735 by the relevant authority, the incident shall be unforeseeable and unavoidable.
The determination whether or not an incident qualifies as unforeseeable or
unavoidable on a case by case basis.
Accordingly, should authority determine
that impossibility to perform did not arise out of the government contractor’s
acts or omission, the contractor could not afford to remove such obstacle and the
situation constitutes an obstacle in fulfilling the contractual obligations. It
can be decided to give additional time extension or terminate the contract upon
determining; that the situation did not arise out of contracting parties’
commitment or omission,
Since, the determination will be made on case by case basis and precedents indicates inconsistent decisions by the authorities, Herdem Attorneys at Law, highly recommends government contractors to be diligent in their applications. If you have any question regarding this alert, please feel free to contact covid19@herdem.av.tr
Author: Şafak Herdem